4Preliminary Knowledge4.1Personnel
Qualified oversight is a prerequisite to the successful implementation of pipeline repair practices.Regulatoryrequirements for the qualification of pipeline personnel performing repair activities are covered in DOT Regulation 49CFR 195.501 through 195.509 of Subpart G (Operations and Maintenance). Guidance for the development andimplementation of operator qualification (oQj programs and procedures are given in ASME B31Q,PipelinePersonnel Qualification, and in APl 1161,Guidance Document for the Qualification of Liquid Pipeline Personnel.Personnel working on pipeline repairs must understand the importance of careful planning to ensure safe and efficientpractices and procedures. Employees and contractors should be brieled on-site about specific repairs and safetyprocedures. Only personnel with the proper training, experience and demonstrated skills should be allowed toperform pipeline repairs.
4.2Safety Procedures
Repair personnel shall have a basic knowledge of safety procedures that includes, but is not limited to, lockouthtagout(LoTO); confined space;worker’s right-to-know,personal protective equipment; excavation and trenching; fireprevention and protection; emergency response; atmospheric testing devices; hot work; work permitting; respiratoryprotection; hydrogen sulfide;hearing conservation;first aid;hazardous substances; fall protection; ergonomics;electrical hazards; and abrasive blasting; Regulations to protect worker safety are covered in oSHA 29 CFR 1910(operations) and 29 CFR 1926(construction).
The company person or designee with overall responsibility for the repair should review previous testing and repairfiles to determine the presence or absence of asbestos-containing pipe coatings, lead-based paint,or othersubstances requiring special attention. lf coatings are identified to contain hazardous substances,special workpractices designed by the company’s health and safety department to mitigate employee exposure should be used.Additional handling and disposal requirements may be specified by local, state,,or federal agencies,consultregulations in your area to determine and develop appropriate handling procedures.
ln addition, the company person or designee with overall responsibility for the repair should be knowledgeable aboutthe most recent Department of Transportation Alert Notices and Natinal Transportation Safety Boardrecommendations related to pipelines as they may pertain to the specific repair situation.
5 Pre-departure Practices
5.1General
When piping revisions, replacements, or repairs are needed, the goal is to safely and efficiently complete the work.Work shall include in-service and out of service repairs. To ensure the safe and efficient completion of the repairproject, the proper preplanning and groundwork shall be accomplished before any work is done.
5.2Preplan Procedures
The preplan should include the following steps.
a) Consult and comply with all applicable laws and regulations.
b) Notfy “ONE CALL” service, if provided in the area or, if not, contact the owners of the buried facilities directly,
giving notice of the work and allowing ample time for other buried facilities to be located and marked.(811National One Call number.)
c) Evaluate reported damage and determine if a Safety-related Condition Report should be filed with the Department
of Transportation.
d) Evaluate reported damage and determine appropriate repair method required to mitigate the condition.
e) Develop a written work plan that includes the proper repair procedure, drain-down or isolation procedures and
appropriate equipment required to complete the repair project safely and efficiently.
f)Determine pipeline operating characteristics required during the repair project .Determine if pipeline pressure de
rating and/or shut down is required to complete the repair project safely.
g)Obtain any required permits, including landowner, local govermnment, other regulatory agencies, company general
and hot work permits, if required.
h) Ensure all tools and safety equipment is in good working order.
i) Brief all line repair personnel on the proper safety procedures and preplan requirements.
j) Notify personnel at the control center and discuss the line repair plans. Pipeline flow conditions, such as pressure
and flow rate at the site of the repair, should be considered prior to the actual initiation of the repair.In servicerepairs may require reduced operating characteristics and specific flow or no-flow conditions dependent uponspecific operator procedures. Out of service repairs or replacements may require line shut down, isolation, andevacuation prior to work initiation. Emergency procedures should also be reviewed with the control centerpersonnel.
k) Ensure adequate fire protection equipment is available for emergencies and during welding or hot work activities.l) Ensure all communications equipment is in good working order and establish a procedure for the control center to
monitor the job’s progress.
m) Ensure all communications and other electronic equipment is intrinsically safe or ensure that this equipment wl
be used a safe distance from potential vapor sources.
n) Close, lock, and tag the valves connected to the line section to be repaired, if line is required to be isolated and
taken out of service during the repair completion.
o)Open, lock, and tag the circuit breakers on any pumps and motor operated valves that could affect the safety of
the job.
p)Open, lock, and tag the circuit breakers on any rectifierIground bed installations that could affect the safety of the
job.